20,000+ Professional Language Experts Ready to Help. Expertise in a variety of Niches.
Unmatched expertise at affordable rates tailored for your needs. Our services empower you to boost your productivity.
GoTranscript is the chosen service for top media organizations, universities, and Fortune 50 companies.
Speed Up Research, 10% Discount
Ensure Compliance, Secure Confidentiality
Court-Ready Transcriptions
HIPAA-Compliant Accuracy
Boost your revenue
Streamline Your Team’s Communication
We're with you from start to finish, whether you're a first-time user or a long-time client.
Give Support a Call
+1 (831) 222-8398
Get a reply & call within 24 hours
Let's chat about how to work together
Direct line to our Head of Sales for bulk/API inquiries
Question about your orders with GoTranscript?
Ask any general questions about GoTranscript
Interested in working at GoTranscript?
Speaker 1: Hi everybody, my name is Charu Behl and I'm a consultant at EPMA. Today I'm going to talk about various methods to update your schedule using Microsoft Project 2013. Now basically there are three methods to update your project progress and the method you choose to update depends on the nature of work being performed in your organization. Now the very first method I'm going to explain is called the percent complete method. It is an estimated ratio of actual work performed versus total amount of work to be completed. Now to do that the very first step that I would do is, I would right-click and insert a column called person complete column. Once I do that I would go under the view ribbon and under the tables drop-down I would select the tracking table. Now here you would see the two columns called the actual start and the actual finish. A lot of time what happens is that due to the schedule slippage your actual start date is different from what you had planned earlier and you want to make sure that the task A is reported on time. So for example in this task instead of starting on the 10-6 schedule start date it starts on 10-13 and you see what happens Microsoft Project automatically pushes out the schedule by a week and now I once I know my actual start date I can actually go back to my entry table and select the task that I want to update. Under the task ribbon and under the schedule section I can see all these bars varying from 0% to 100%. Now once I mark my project task is 100% complete there is this right or check mark that appears in the indicator section showing that the task is 100% complete. And one very interesting thing that you would want to see is that once the task is complete the actual finish date is automatically populated as the schedule finish date. The second method is called the actual work and remaining work method. It is a measure of total actual work hours performed to date and the estimated number of work that has remaining. Now again to update task B I would want to make sure that my actual start date is correct. Assuming that it started as planned I would go under the view ribbon and under my tables I will select the work table. Now in this table you would see these two columns called as the actual work and the remaining work column. Now to update task B you see that the schedule work or the planned work was for 96 hours and the actual work that has been done till now is 0% that means 0 hours and remaining is 96 hours of work. Now once I mark this task as 50% complete you see what happens remaining is 48 and actual is 48 as well. And once I mark it as 100 the actual is 96% and the remaining is 0%. This method is a little better than the percent complete method because it actually gives manager the flexibility to put in the actual number of hours. Now for example the number of hours that were actually put into this task were more than say 96 hours. So what happens if I enter 104 hours? You see that again the scheduling engine makes way for 104 hours and the schedule is pushed out by a day. Now the third method is called the actual work per period and it is a measure of actual work performed during each time period which may vary from a week to a day to a month depending on your organization and the estimated number of work hours remaining. Now to do that I would again go under the view section and under the table drop-down menu I would select the work and now under the view I would select my task usage view and okay so now you see on the right hand side how my task is divided on basis of day. So now the manager or the scheduler has the ability to break it down to the number of days and there is an increased granularity to the whole process. Now for task C I would insert I would right-click and say actual work. Okay now you can actually see where my task starts right here and now on Monday suppose my resource works as planned and you see how everything changes. What if on the next day instead of eight hours my resource only works for six hours. You see how the actual is automatically updated to six hours and the plan is updated to six hours and the remaining two hours get scheduled once this task is over. Now this is again a very flexible method that a manager can use to update his or her schedule. Keep watching out for more videos and quick tips. You can also visit our website. I hope you enjoyed the video. Goodbye for now.
Generate a brief summary highlighting the main points of the transcript.
GenerateGenerate a concise and relevant title for the transcript based on the main themes and content discussed.
GenerateIdentify and highlight the key words or phrases most relevant to the content of the transcript.
GenerateAnalyze the emotional tone of the transcript to determine whether the sentiment is positive, negative, or neutral.
GenerateCreate interactive quizzes based on the content of the transcript to test comprehension or engage users.
GenerateWe’re Ready to Help
Call or Book a Meeting Now